Construction of roads & water, Wastewater, storm water & irrigation utilities within the extent of the promenade.
· Water Network:
- The Project includes the following :
- Supply and Construct DI pipes of 200mm, 250 mm and 300mm pipes for water distribution main including all appurtenances, fittings and valves .
- Supply and construct HDPE pipes of 125mm, 63mm and 32mm pipes, and about 44 No.s house connections, including all fitting and valves .
· Roads work :
The Project includes the construction of approximately 2.5 Km of roads, including 9m wide Promenade, two roundabouts and a 7m width access road connecting to the existing Dead Sea Highway service road .
· Wastewater Collection Network :
- The Project includes the supply and construction of the following:
- UPVC gravity pipe lines of 200mm diameter .
- House connection of 150 mm diameter .
- DI force main pipes of 200mm diameter including all fittings & all types of manholes and fittings .
· Irrigation Distribution Network :
- HDPE main lines of 125mm, 110mm, 50mm and 32mm diameters with total lengths of 635m. 2200m, 500m respectively including all appurtenance, fittings, and isolating valves
- Electrical field wiring, armoured cable 2X4mm of 3000m.
- Storm water collection Network :
- GRP pipe lines of 800mm, 700mm and 600mm, and U-PVC pipe lines of 500mm, 400mm and 300mm diameters and all type of manholes, water inlets and fittings
Concrete pipe and box culverts .